Adams County Courthouse
ADAMS COUNTY COURTHOUSE Infrastructure Modernization
TEN completed a comprehensive energy project for the Adams County Courthouse and adjacent facilities, delivering both immediate energy savings and long-term operational improvements.


By The
Numbers
- $126379M
Project Size
- $126379K
Annual Guaranteed Savings
- $126379K
Annual Savings

TEN's Project
Team Delivered
- Upgraded all facility lighting to LED
- Integrated existing mechanical equipment into the building automation system
- Corrected building automation system deficiencies and optimized programming
- Updated aging mechanical equipment
- Improved building envelope (sweep, astragals, window treatments)
- Installed ozone laundry systems in the prison
- Verified and corrected sewage building errors
- Completed retro-commissioning of all systems and equipment
- Converted variable air volume boxes to direct digital controls in the Courthouse
- Installed variable frequency drives on the Courthouse's chilled water pump and hot water pumps at the Humane Services Building
- Replaced prison chillers, hot water heaters, and boilers via the work release program
- Installed new rooftop units via the work release program
- Replaced air-handling unit and interior panes